Neighbors - DOT informed us late yesterday that the disruptive (i.e. noisy) work to remove concrete pavement is expected to begin in July 24th. For sound mitigation during jack hammering, the contractor will use noise reducing tent enclosures comprised of sound blankets and smaller equipment to the extent possible. In addition, single-lane weeknight closures from 12:01 a.m. to 5:00 a.m. on the Queens-bound BQE will begin on July 20th and will continue for about eight weeks. Work on the Columbia Street ramps is anticipated to be complete by July 28th but DOT is working with the contractor to condense the schedule and open the sidewalk and ramps earlier if possible. Please find the flyer detailing the work here. If you have specific questions about the upcoming work, please attend a meeting organized this week by DOT on Thursday, July 20th at 4:00pm. The meeting will be attended by the BHA, elected officials, DOT staff and members of the public. You must register in advance. After registering, you will receive a confirmation email containing information about joining the meeting. If you missed the earlier information session on June 29th, you can review the meeting on DOT's website or YouTube. The BHA will continue to update the community throughout the process, but we recommend you join DOT's email update list by reaching out to Community Liaison, Anita Navalurkar at (347) 647-0876 or anavalurkar.consultant@dot.nyc.gov. |